Successful 2022 Eudunda Christmas Party AGM

Thank you to all who came to our AGM , we had a fantastic turnout ! The Eudunda Christmas Party Committee takes on the task of running Eudunda’s Annual Christmas Party. This committee is actually a sub-committee of the Eudunda Community, Business and Tourism Association (ECBAT). Eudunda Christmas Party Committee …

Read more

Renewable Energy Projects Update Report – 31st March 2022 From Mel

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 MARCH 2022 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet are managing the construction of the transmission line & power substations for the project & the section between Robertstown & …

Read more

Eudunda Caravan Park Update Report January 2022

This is an update report on the progress being achieved on the project to purchase two 2 bedroom cabins for additional accommodation for the Eudunda Caravan Park. The Eudunda Caravan Park currently has 8 powered sites managed by Steve & Lee Wegener and over the last year the occupancy and …

Read more

SA Water – Morgan Whyalla Pipeline Renewal

SA Water announced on 10 January 2022, that they are planning to replace sections of the Morgan Whyalla pipeline commencing in March 2022. The pipeline is a 358 kilometre long, above ground pipeline that was constructed in the 1940’s for the transfer of bulk water supplies to the Iron Triangle …

Read more

Renewable Energy Projects Update Report – November 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 30 NOVEMBER 2021 1 Neoen – Goyder Renewables Zone Stage 1,2 & 3 – South of Burra & North of Robertstown near Koonoona Road, World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are …

Read more