REGIONAL COUNCIL OF GOYDERRENEWABLES ENERGY PROJECTS UPDATE REPORT23 DECEMBER 2022 1 NEOEN – GOYDER RENEWABLES ZONE Stage 1,2 & 3 – South of Burra & north of Robertstown near World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are now commencing South Stage 1A …
The Eudunda Community Business & Tourism Committee would like to invite you to become a business member. With your backing our committee can continue towards making our town and region a great place to live, work and play. If you or your business have not been contacted yet – please …
E.C.B.A.T. invites you to Goyder Business Breakfast Thursday October 27th 7am Burra Town Hall Goyder Business Breakfast Join us for an introductory breakfast to find out more about establishing a representative organisation for businesses in the Goyder area. Guest Speakers: Jeremy Carn – Ausindustry Cathie Brown – Leaders Institute of …
REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 AUGUST 2022 NOTE: New Project Added To The Report – see 7 WHYTE YARCOWIE WIND FARM 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet are managing the construction of the …
Regional Development Australia Yorke and Mid North SA are developing a regional drought resilience plan to assist farmers, businesses and communities plan for future droughts in the Northern and Yorke region and they want to hear from you! You can share your story and experience here: This 3 question survey …
Eudunda: 12th April 4:30pm to 7pm Eudunda RSL Rooms RSVP to Julian Marchant by 8 April 2022 Join us to explore drought resilience from a farm, business supply chain, health and community perspective. As part of the ongoing community engagement process regarding drought resilience, a series of workshops are being …
REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 MARCH 2022 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet are managing the construction of the transmission line & power substations for the project & the section between Robertstown & …
This is an update report on the progress being achieved on the project to purchase two 2 bedroom cabins for additional accommodation for the Eudunda Caravan Park. The Eudunda Caravan Park currently has 8 powered sites managed by Steve & Lee Wegener and over the last year the occupancy and …
SA Water announced on 10 January 2022, that they are planning to replace sections of the Morgan Whyalla pipeline commencing in March 2022. The pipeline is a 358 kilometre long, above ground pipeline that was constructed in the 1940’s for the transfer of bulk water supplies to the Iron Triangle …
REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 30 NOVEMBER 2021 1 Neoen – Goyder Renewables Zone Stage 1,2 & 3 – South of Burra & North of Robertstown near Koonoona Road, World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are …
REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 AUGUST 2021 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet have announced on 31 May 2021 that the Australian Energy Regulator has approved the expenditure of $2.28 billion to deliver …