Renewable Projects Update – SEPTEMBER 2020
ROBERTSTOWN POWER SUBSTATION UPGRADE – Upgrade & expansion of the power substation in readiness for the connection of the other renewables projects to the substation over the next years. The project commenced in March 2020 & is expected to be completed by December 2020. Enerven, the principal electrical contractor currently …