REGIONAL COUNCIL OF GOYDERRENEWABLES ENERGY PROJECTS UPDATE REPORT30 APRIL 2023 1 NEOEN – GOYDER RENEWABLES ZONE Stage 1,2 & 3 – South of Burra & north of Robertstown near World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & have now commenced Goyder South Stage …

Read more

Australia Day Breakfast – Eudunda – 26th Jan 2023

Australia Day Breakfastand Community PresentationsIn the Centenary Gardens – EudundaincludingCitizen of the Year and Community Event of the Yearand Awards for Best presented Properties (Tidy Towns) Free Breakfast from 8:00am catering by Eudunda Community Hub & ShedPresentations at 9am Event Sponsored by the Regional Council of GoyderEvent Coordinated by the …

Read more

Renewable Energy Projects Update Report – 23rd December 2022 From Mel

REGIONAL COUNCIL OF GOYDERRENEWABLES ENERGY PROJECTS UPDATE REPORT23 DECEMBER 2022 1 NEOEN – GOYDER RENEWABLES ZONE Stage 1,2 & 3 – South of Burra & north of Robertstown near World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are now commencing South Stage 1A …

Read more

Renewable Energy Projects Update Report – 31st August 2022 From Mel

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 AUGUST 2022 NOTE: New Project Added To The Report – see 7 WHYTE YARCOWIE WIND FARM 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet are managing the construction of the …

Read more

Renewable Energy Projects Update Report – 31st March 2022 From Mel

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 MARCH 2022 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet are managing the construction of the transmission line & power substations for the project & the section between Robertstown & …

Read more

Eudunda Caravan Park Update Report January 2022

This is an update report on the progress being achieved on the project to purchase two 2 bedroom cabins for additional accommodation for the Eudunda Caravan Park. The Eudunda Caravan Park currently has 8 powered sites managed by Steve & Lee Wegener and over the last year the occupancy and …

Read more

SA Water – Morgan Whyalla Pipeline Renewal

SA Water announced on 10 January 2022, that they are planning to replace sections of the Morgan Whyalla pipeline commencing in March 2022. The pipeline is a 358 kilometre long, above ground pipeline that was constructed in the 1940’s for the transfer of bulk water supplies to the Iron Triangle …

Read more

Renewable Energy Projects Update Report – November 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 30 NOVEMBER 2021 1 Neoen – Goyder Renewables Zone Stage 1,2 & 3 – South of Burra & North of Robertstown near Koonoona Road, World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are …

Read more

Renewable Energy Projects Update Report – August 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 AUGUST 2021 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet have announced on 31 May 2021 that the Australian Energy Regulator has approved the expenditure of $2.28 billion to deliver …