Eudunda Caravan Park Update Report January 2022

This is an update report on the progress being achieved on the project to purchase two 2 bedroom cabins for additional accommodation for the Eudunda Caravan Park. The Eudunda Caravan Park currently has 8 powered sites managed by Steve & Lee Wegener and over the last year the occupancy and …

Read more

SA Water – Morgan Whyalla Pipeline Renewal

SA Water announced on 10 January 2022, that they are planning to replace sections of the Morgan Whyalla pipeline commencing in March 2022. The pipeline is a 358 kilometre long, above ground pipeline that was constructed in the 1940’s for the transfer of bulk water supplies to the Iron Triangle …

Read more

Renewable Energy Projects Update Report – November 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 30 NOVEMBER 2021 1 Neoen – Goyder Renewables Zone Stage 1,2 & 3 – South of Burra & North of Robertstown near Koonoona Road, World’s End & Bright. Neoen are the Developers, Owners & Operators of the project & are …

Read more

Renewable Energy Projects Update Report – August 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 31 AUGUST 2021 1 Electranet Project Energy Connect – Interconnector From the Robertstown Power Substation to the SA/NSW border. Electranet have announced on 31 May 2021 that the Australian Energy Regulator has approved the expenditure of $2.28 billion to deliver …

Read more

Renewables Projects Update – June 2021

REGIONAL COUNCIL OF GOYDER RENEWABLES ENERGY PROJECTS UPDATE REPORT – 1 JUNE 2021   1 Electranet Project Energy Connect – Interconnector Electranet have announced on 31 May 2021 that the Australian Energy Regulator has approved the expenditure of $2.28 billion to deliver the project from Robertstown to Wagga Wagga in …

Read more

ECBAT Thank All Volunteers in the Region

The Eudunda Community, Business and Tourism Committee would like to acknowledge and thank all the Volunteers in our Region. National Volunteer Week is the annual celebration to acknowledge the generous contribution of our nation’s volunteers. Thank you to all volunteers for the vital role you play each and every day, …

Read more

ECBAT Announce Eudunda Caravan Park Cabin Purchase Project

The Eudunda Community Business & Tourism Committee (ECBaT) & the Eudunda Caravan Park Subcommittee are excited to announce a further extension to the facilities available at the Eudunda Caravan Park. The park currently has 8 powered sites after increasing the number of sites by 4 in November 2020. The next …

Read more

Renewables Projects Update – March 2021

ROBERTSTOWN POWER SUBSTATION UPGRADE This project involves an upgrade & expansion of the power substation in readiness for the connection of other renewables projects to the substation over the next years. The project commenced in March 2020 & is expected to be completed by June 2021. Enerven, the principal electrical …